Second Street is open again between Church Street and Touline Street, ending a closure that began with concrete and utility work in June and kept the Touline intersection blocked into this week.
The City of Natchitoches said Thursday that the reopening includes the east side of the Second Street–Touline Street intersection. Drivers who have been detouring around that corner can use Second Street through downtown again. The city asked motorists to watch temporary signs and other traffic-control devices while work continues nearby.
The intersection had stayed closed after new concrete went down. Crews poured the east side last week and the west side on September 29. The city held traffic off the new pavement until compressive-strength tests showed it could carry vehicles, a step officials had expected no later than the middle of the week of October 5–9.
During the 20th annual Classic Car Show on October 2–3, the east side was used only to stage vehicles. Other traffic was kept off so the fresh concrete would not be damaged and the reopening delayed.
Work is not finished. Over the next few weeks, crews will keep replacing concrete on Touline Street west of Second.
In the current phase, Touline is closed from Second Street west to the west-most driveway into the Natchitoches Parish Library. After that section is opened, the city has said the work will continue west toward Fourth Street.
An earlier notice described the next cut as running from Second Street to a point just west of the library’s eastern driveway, starting on or about October 5.
The project is larger than this one intersection. Construction began in June on deteriorated concrete along Second Street, with water and sewer line replacement, storm-drain work, and ADA curb ramps included.
The first phase ran from Church Street to Trudeau Street and included a new sewer manhole at Church. Crews then moved from Trudeau to Touline.
The overall job covers Second Street from Church to Touline and Touline from Front Street toward Fifth Street.
Skyplex Trucking LLC of Natchitoches holds the contract, reported at about $2.3 million.
Funding is a State Capital Outlay award — earlier notices cited $2.2 million — with the state covering 75 percent and the city putting up a 25 percent match.
Nearby water and sewer service was expected to stay on except for short tie-ins.