Two Mile Street Reopens Following Major Pavement Project

NATCHITOCHES, La. — Two Mile Street will reopen to traffic Saturday following completion of a major pavement replacement project, according to the City of Natchitoches.

The section between Second Street and Fourth Street had been closed for construction but will reopen Nov. 21 and remain open through the Christmas and New Year holidays.

City officials said pavement replacement work on the segment has been completed as part of a project costing nearly $2.4 million. Approximately 75 percent of the funding was provided through Louisiana’s Capital Outlay Program.

Following the holiday season, Two Mile Street will close again to through traffic as crews replace deteriorated concrete pavement from the Natchitoches Parish Library to Fifth Street.

City officials have not announced a specific closure date for the next phase of construction.